Solar PV and BESS hybrid power plant, West Africa

Project 01 / 06

Aerial view of a solar and battery storage plant on red laterite earth in West African savanna, with a mine haul road and open-pit workings in the hazy distance.
Sector
Solar PV and battery storage
Scale
33 MWp
Status
In construction
Engaged by
Soventix GmbH (EPC contractor)

A utility-scale solar plant with battery storage, built to supply a mining operation with reliable, lower-carbon power. The site is remote, the supply chain runs through three continents, and the plant must integrate with the mine’s existing power system.

Our role: Senior Project Manager leading end-to-end EPC delivery, reporting to the COO.

What we did

  • Directed a 20-strong project team across engineering, procurement, logistics, subcontracting, insurance and commercial workstreams.
  • Negotiated the principal Supply and Installation Agreements with the client’s legal and commercial teams, settling positions on commissioning liability, retention and delivery risk.
  • Structured and negotiated multi-million dollar subcontracts for civil, mechanical and electrical scopes, from first redline to counter-signature.
  • Mobilised a site workforce of 450.
  • Ran international logistics for 41 shipments and more than 170 containers of modules, mounting structures, inverters and battery units.
  • Set up shipment tracking, goods receipt inspection protocols and supplier performance controls to protect the commissioning critical path.
  • Prepared variation orders for client approval and managed formal instructions to subcontractors.
Five wind turbines in silhouette against the last orange light on the horizon, with rows of solar panels catching a thin line of sky in the dark foreground.